Corporation Road Bridge Update: Footway closures and weekend working in March 2025

Chris

2/28/2025 11:54:31 AM

Business

4 mins read

Complex engineering work continues to grade II listed structure, Corporation Bridge.

 

Grit blasting continues to Span 5 and 6, alongside priming, chipping of excessive corrosion and substructure repair works.

 

Control room works are complete with painting in progress underneath as scaffolding is removed from Spans 2 and 3.

 

To take advantage of anticipated low tide levels, weekend working will take place next month.

 

Footway closures are also required whilst works are taking place adjacent to public areas to ensure the safety of both the public and the workers on site.

 

To help complete remaining sections of the works the footway may be closed for 2-days a week if conditions allow.

 

Footway closures will take place between 9am and 4pm each weekday as detailed below. The footway will remain open during the weekend working dates. Temporary signs will be in place for the footway closures.

 

 

March 2025 weekend working and footway closure dates:

 

South Footway Closures

 

  • Wednesday 5 March

 

  • Thursday 6 March

 

  • Tuesday 11 March

 

  • Wednesday 12 March

 

  • Wednesday 19 March

 

  • Thursday 20 March

 

  • Wednesday 26 March

 

  • Thursday 27 March

 

Weekend working

 

  • Saturday 8 March and Sunday 9 March

 

  • Saturday 22 March and Sunday 23 March

 

North East Lincolnshire Council, its delivery partner, Equans, and contractor, Spencer Group, would like to thank the public for their patience whilst the work is being undertaken.

 

As Corporation Road Bridge is a construction site, it is important that the public respect the access restrictions in place, which have been introduced for safety reasons. Members of the public are reminded to please stay outside of all encapsulated and other working areas for their own safety, as well as that of those working there.

 

Visit www.nelincs.gov.uk/corporation-road-bridge-major-restoration  to keep up to date with the Corporation Road Bridge works.

Other Articles You Might Like

Chris

7/26/2024 9:19:14 AM

Celebrate the 24 free parks available across Grimsby and Cleethorpes this summer
Love Parks Week begins today (July 26 -August 4 2024) and what better time to appreciate our outdoor spaces and to take ...
Nature 4 min read

Chris

11/25/2024 11:27:50 AM

Letter sent to Secretary of State to try keep Post Office in Grimsby
Work to try to avert a potential blow to Grimsby’s high street has been high on the priority list this week.
Business 3 min read

Chris

7/15/2024 7:29:49 PM

North East Lincolnshire: the place to be for young women and girls
A recent North East Lincolnshire Council-led skills fair highlighted the career opportunities that exist in our borough ...
Education 2 min read

Stuart

12/14/2023 3:07:18 PM

International Bomber Command Centre celebrates record breaking year
THE INTERNATIONAL Bomber Command Centre (IBCC) in Lincolnshire is celebrating a record-breaking year that’s on course to...
Achievements 3 min read