Home > Latest News > Business > Corporation Road Bridge Update: Footway closures and weekend working in March 2025

Corporation Road Bridge Update: Footway closures and weekend working in March 2025

Chris

2/28/2025 11:54:31 AM

Business

4 mins read

Complex engineering work continues to grade II listed structure, Corporation Bridge.

 

Grit blasting continues to Span 5 and 6, alongside priming, chipping of excessive corrosion and substructure repair works.

 

Control room works are complete with painting in progress underneath as scaffolding is removed from Spans 2 and 3.

 

To take advantage of anticipated low tide levels, weekend working will take place next month.

 

Footway closures are also required whilst works are taking place adjacent to public areas to ensure the safety of both the public and the workers on site.

 

To help complete remaining sections of the works the footway may be closed for 2-days a week if conditions allow.

 

Footway closures will take place between 9am and 4pm each weekday as detailed below. The footway will remain open during the weekend working dates. Temporary signs will be in place for the footway closures.

 

 

March 2025 weekend working and footway closure dates:

 

South Footway Closures

 

  • Wednesday 5 March

 

  • Thursday 6 March

 

  • Tuesday 11 March

 

  • Wednesday 12 March

 

  • Wednesday 19 March

 

  • Thursday 20 March

 

  • Wednesday 26 March

 

  • Thursday 27 March

 

Weekend working

 

  • Saturday 8 March and Sunday 9 March

 

  • Saturday 22 March and Sunday 23 March

 

North East Lincolnshire Council, its delivery partner, Equans, and contractor, Spencer Group, would like to thank the public for their patience whilst the work is being undertaken.

 

As Corporation Road Bridge is a construction site, it is important that the public respect the access restrictions in place, which have been introduced for safety reasons. Members of the public are reminded to please stay outside of all encapsulated and other working areas for their own safety, as well as that of those working there.

 

Visit www.nelincs.gov.uk/corporation-road-bridge-major-restoration  to keep up to date with the Corporation Road Bridge works.

Other Articles You Might Like

Chris

3/4/2025 1:31:35 PM

Still time to give your views on introduction of Selective Licensing scheme
A public consultation on the introduction of a Selective Licensing scheme in parts of the East Marsh reaches its halfway...

Chris

8/26/2025 8:53:50 AM

Weekly food waste scheme will help secure green future and new opportunities for North East Lincolnshire
The Council’s Cabinet has welcomed the introduction of weekly food waste collections to help improve waste and recycling...

Chris

9/3/2024 1:40:27 PM

Minor improvements to bus services announced for North East Lincolnshire
North East Lincolnshire Council and Stagecoach East Midlands are pleased to announce minor amendments to some of their m...
Transport 4 min read

Chris

6/9/2025 12:17:21 PM

South Holland organisations encouraged to apply for grants as Lincolnshire Community Foundations UKSPF GRASSroots scheme reopens
Community organisations, village hall committees, parish councils and sports clubs are being encouraged to apply for a g...