Recent works have seen parts of the scaffolding and encapsulation removed from the structure, whilst other areas have been covered over to protect the environment from debris.
Works to refurbish the control room are almost complete and grit blasting is in progress to the areas under the structure to enable inspections to take place to determine the condition.
To take advantage of anticipated low tide levels, weekend working will take place next month. Footway closures are also required whilst works are taking place adjacent to public areas to ensure the safety of both the public and the workers on site.
Footway closures will take place between 9am and 4pm each weekday. The footway will remain open during the weekend working dates. Temporary signs will be in place for the footway closures.
December 2024 weekend working and footway closure dates:
South Footway Closures
Weekend Working
North East Lincolnshire Council, its delivery partner, Equans, and contractor, Spencer Group, would like to thank the public for their patience whilst the work is being undertaken.
As Corporation Road Bridge is a construction site, it is important that the public respect the access restrictions in place, which have been introduced for safety reasons. Members of the public are reminded to please stay outside of all encapsulated and other working areas for their own safety, as well as that of those working there.
Visit InvestNEL | Corporation Road Bridge Major Restoration - InvestNEL to keep up to date with the Corporation Road Bridge works.
Stuart
4/3/2024 9:02:33 AM
Stuart
12/19/2023 11:44:21 AM
Chris
12/2/2024 3:13:00 PM
Stuart
1/10/2024 1:25:28 PM