Corporation Road Bridge update: Footpath closures and weekend working in June 2024

Stuart

5/29/2024 10:21:48 AM

Transport

3 mins read

Works to Grade II listed structure, Corporation Road Bridge, have been progressing.

The steel work repairs are ongoing to both sides of the bridge deck. Whilst painting works continue, works to refurbish the control room are also making good progress, with restoration to timbers, window preparations and external panelling all well underway. Insulation works and roof repairs are also in progress.

To continue the mechanical preparation works to the underdeck of the bridge, weekend working is required due to expected low tidal levels. Footpath closures are also required whilst works are undertaken adjacent to public areas to ensure the safety of both the public and the contractor.

Footpath closures will take place between 9am and 4pm each weekday. The footway will remain open during the weekend working dates. Temporary signs will be in place for the footway closures.

June 2024 weekend working and footway closure dates:

North East Lincolnshire Council, its delivery partner, Equans and contractor Spencer Group would like to thank the public for their patience whilst the work is being undertaken.

Visit InvestNEL | Corporation Road Bridge Major Restoration - InvestNEL to keep up to date with the Corporation Road Bridge works.

Other Articles You Might Like

Chris

2/4/2025 12:07:55 PM

Nearly 400,000 visitors recycle more than the weight of the Eiffel Tower at tip in 2024
Users at the tip brought over 7900 tonnes of plastic, glass, cans and paper to the Community Recycling Centres in the la...
Achievements 4 min read

Chris

4/29/2025 9:24:28 AM

Lincoln Cathedral volunteers taking part in historic Opus Anglicanum embroidery project
The volunteers who make up Lincoln Cathedral Needlework Guild are taking part in a national project to create one of the...
Achievements 4 min read

Chris

2/18/2025 9:54:43 AM

Essential works commence ahead of new restrictions on Station Road, New Waltham
Works are currently underway to complete essential lining and signage work to implement the traffic regulation orders in...
Business 3 min read

Chris

11/6/2025 9:35:50 AM

Keepmoat plans to invest more than £20 million into transformation of Alexandra Dock
Sent out on behalf of Keepmoat
Business 4 min read