Corporation Road Bridge update: Footpath closures and weekend working in July 2024

Chris

7/3/2024 11:02:45 AM

Transport

4 mins read

Works to Grade II listed structure, Corporation Road Bridge, have been progressing.

 

Application of the primer and paint coatings has also been ongoing along with required preparation works and inspections. Control room works are in progress and all rotten timbers have now been replaced and corroded steels are due to be replaced. Insulation works are complete and roof replacement works will commence soon.

 

Mechanical preparation works to the underdeck of the bridge on Spans 1 to 4 are complete and painting is in progress on spans 1 to 3. To take advantage of anticipated low tide levels, weekend working is required. Footpath closures are also required whilst works are taking place adjacent to public areas to ensure the safety of both the public and the contractor.

 

Footpath closures will take place between 9am and 4pm each weekday. The footway will remain open during the weekend working dates. Temporary signs will be in place for the footway closures.

 

July 2024 weekend working and footway closure dates

Footway closures:

Wednesday 3 July

Wednesday 10 July

Thursday 11 July

Wednesday 17 July

Wednesday 24 July

Thursday 25 July

 

Weekend working:

13 and 14 July

 

North East Lincolnshire Council, its delivery partner, Equans and contractor, Spencer Group, would like to thank the public for their patience whilst the work is being undertaken.

 

As Corporation Road Bridge is a construction site, it is important that the public respect the access restrictions in place, which have been introduced for safety reasons.  Members of the public are reminded to please stay outside of all encapsulated and other working areas for their own safety, as well as that of those working there.

 

Visit InvestNEL | Corporation Road Bridge Major Restoration - InvestNEL to keep up to date with the Corporation Road Bridge works.

Other Articles You Might Like

Chris

8/8/2025 10:24:24 AM

Scam warning issued as residents get winter payment texts
A warning has been issued by Council officers after some residents living in other parts of the region complained of rec...

Chris

2/16/2026 4:12:49 PM

Highways teams are working hard to tackle winter potholes across North East Lincolnshire
North East Lincolnshire Council’s Highways team is working around the clock to repair a surge in potholes caused by this...
Transport 4 min read

Chris

10/17/2024 12:57:44 PM

Grant funding for decarbonisation keeps NELC on path to net zero
North East Lincolnshire Council, in partnership with Equans, has secured a grant of £62,332.50 from the Department for E...
Business 4 min read

Chris

4/8/2025 10:00:58 AM

Reminder - you need to be registered to vote in this year's elections - deadline on Friday 11 April
The deadline to make sure you're on the register to be able to vote in this year's elections is this Friday (11 April).