Corporation Road Bridge update: Footpath closures and weekend working in July 2024

Chris

7/3/2024 11:02:45 AM

Transport

4 mins read

Works to Grade II listed structure, Corporation Road Bridge, have been progressing.

 

Application of the primer and paint coatings has also been ongoing along with required preparation works and inspections. Control room works are in progress and all rotten timbers have now been replaced and corroded steels are due to be replaced. Insulation works are complete and roof replacement works will commence soon.

 

Mechanical preparation works to the underdeck of the bridge on Spans 1 to 4 are complete and painting is in progress on spans 1 to 3. To take advantage of anticipated low tide levels, weekend working is required. Footpath closures are also required whilst works are taking place adjacent to public areas to ensure the safety of both the public and the contractor.

 

Footpath closures will take place between 9am and 4pm each weekday. The footway will remain open during the weekend working dates. Temporary signs will be in place for the footway closures.

 

July 2024 weekend working and footway closure dates

Footway closures:

Wednesday 3 July

Wednesday 10 July

Thursday 11 July

Wednesday 17 July

Wednesday 24 July

Thursday 25 July

 

Weekend working:

13 and 14 July

 

North East Lincolnshire Council, its delivery partner, Equans and contractor, Spencer Group, would like to thank the public for their patience whilst the work is being undertaken.

 

As Corporation Road Bridge is a construction site, it is important that the public respect the access restrictions in place, which have been introduced for safety reasons.  Members of the public are reminded to please stay outside of all encapsulated and other working areas for their own safety, as well as that of those working there.

 

Visit InvestNEL | Corporation Road Bridge Major Restoration - InvestNEL to keep up to date with the Corporation Road Bridge works.

Other Articles You Might Like

Chris

6/13/2025 8:39:06 AM

City of Lincoln Council launches Warm Homes Project to tackle fuel poverty and cut carbon emissions
City of Lincoln Council is proud to launch its Warm Homes Project, a new initiative aimed at tackling fuel poverty, redu...

Chris

3/18/2025 10:04:49 AM

UKSPF Funding supports VE and VJ Celebrations in Boston Borough
Boston Borough Council is proud to announce it has received £10,000 in funding from the UK Shared Prosperity Fund (UKSPF...
Business 4 min read

Chris

12/9/2024 12:37:22 PM

Grimsby Top Town Market is ready for Christmas, are you?
Temperatures have dropped, the Christmas lights are up and the most wonderful time of the year is finally here. The mark...
Events 4 min read

Chris

2/24/2025 9:35:09 AM

East Lindsey District Council approves incredible multimillion pound investment to transform local places, communities and businesses
East Lindsey District Council has this week announced the allocation of over £7.8million of investment in the district, ...
Business 4 min read