Home > Latest News > Transport > Corporation Road Bridge update: Footpath closures and weekend working in July 2024

Corporation Road Bridge update: Footpath closures and weekend working in July 2024

Chris

7/3/2024 11:02:45 AM

Transport

4 mins read

Works to Grade II listed structure, Corporation Road Bridge, have been progressing.

 

Application of the primer and paint coatings has also been ongoing along with required preparation works and inspections. Control room works are in progress and all rotten timbers have now been replaced and corroded steels are due to be replaced. Insulation works are complete and roof replacement works will commence soon.

 

Mechanical preparation works to the underdeck of the bridge on Spans 1 to 4 are complete and painting is in progress on spans 1 to 3. To take advantage of anticipated low tide levels, weekend working is required. Footpath closures are also required whilst works are taking place adjacent to public areas to ensure the safety of both the public and the contractor.

 

Footpath closures will take place between 9am and 4pm each weekday. The footway will remain open during the weekend working dates. Temporary signs will be in place for the footway closures.

 

July 2024 weekend working and footway closure dates

Footway closures:

Wednesday 3 July

Wednesday 10 July

Thursday 11 July

Wednesday 17 July

Wednesday 24 July

Thursday 25 July

 

Weekend working:

13 and 14 July

 

North East Lincolnshire Council, its delivery partner, Equans and contractor, Spencer Group, would like to thank the public for their patience whilst the work is being undertaken.

 

As Corporation Road Bridge is a construction site, it is important that the public respect the access restrictions in place, which have been introduced for safety reasons.  Members of the public are reminded to please stay outside of all encapsulated and other working areas for their own safety, as well as that of those working there.

 

Visit InvestNEL | Corporation Road Bridge Major Restoration - InvestNEL to keep up to date with the Corporation Road Bridge works.

Other Articles You Might Like

Chris

5/19/2025 12:20:50 PM

“Without these donations, we couldn’t carry on”: Pet food bank praises Council for Poo Bag Partnership
A North East Lincolnshire food bank has thanked the Council for its help in supporting pet owners across the borough.

Stuart

1/11/2024 3:46:24 PM

North East Lincolnshire Council’s Cabinet set to discuss a pre-let for the Sea Road building in Cleethorpes
Sea Road, in the heart of the town, has been remodelled over the last few years, with the former “Waves” site being demo...
Business 3 min read

Chris

9/15/2025 2:04:28 PM

Lancaster Bomber memorial sculpture installed in North Kesteven
In the last week the On Freedom’s Wings memorial sculpture of a Lancaster Bomber has been installed in situ alongside th...
Achievements 4 min read

Chris

5/6/2025 10:12:01 AM

East Marsh Community Space becomes first Poo Bag Partner!
A local community hub has become the first Poo Bag Partner in North East Lincolnshire Council in an effort to tackle dog...