Corporation Road Bridge update: Footpath closures and weekend working in July 2024

Chris

7/3/2024 11:02:45 AM

Transport

4 mins read

Works to Grade II listed structure, Corporation Road Bridge, have been progressing.

 

Application of the primer and paint coatings has also been ongoing along with required preparation works and inspections. Control room works are in progress and all rotten timbers have now been replaced and corroded steels are due to be replaced. Insulation works are complete and roof replacement works will commence soon.

 

Mechanical preparation works to the underdeck of the bridge on Spans 1 to 4 are complete and painting is in progress on spans 1 to 3. To take advantage of anticipated low tide levels, weekend working is required. Footpath closures are also required whilst works are taking place adjacent to public areas to ensure the safety of both the public and the contractor.

 

Footpath closures will take place between 9am and 4pm each weekday. The footway will remain open during the weekend working dates. Temporary signs will be in place for the footway closures.

 

July 2024 weekend working and footway closure dates

Footway closures:

Wednesday 3 July

Wednesday 10 July

Thursday 11 July

Wednesday 17 July

Wednesday 24 July

Thursday 25 July

 

Weekend working:

13 and 14 July

 

North East Lincolnshire Council, its delivery partner, Equans and contractor, Spencer Group, would like to thank the public for their patience whilst the work is being undertaken.

 

As Corporation Road Bridge is a construction site, it is important that the public respect the access restrictions in place, which have been introduced for safety reasons.  Members of the public are reminded to please stay outside of all encapsulated and other working areas for their own safety, as well as that of those working there.

 

Visit InvestNEL | Corporation Road Bridge Major Restoration - InvestNEL to keep up to date with the Corporation Road Bridge works.

Other Articles You Might Like

Chris

12/13/2024 12:08:13 PM

Mermaid Café building’s bright new future
150 years ago, in 1874, the Mermaid Café building on Cleethorpes North Prom sea front was constructed as a waiting room ...
Business 4 min read

Chris

5/14/2025 8:42:20 AM

Military heritage project recruits local ambassadors
South Kesteven District Council is offering volunteers a chance to research their own community’s airborne forces herita...

Chris

10/30/2024 1:14:28 PM

Don’t let your bonfire plans go up in smoke - notify us now
If you are planning to host a public bonfire in North East Lincolnshire this year, you’ll need to notify the Council, or...

Chris

10/6/2025 9:01:22 AM

Planning a Bonfire? Make Sure to Notify Us
If you are planning to host a public bonfire in North East Lincolnshire this year, you’ll need to notify the Council, or...