Corporation Road Bridge Update: Footway closures and weekend working in May 2025

Chris

5/6/2025 10:15:00 AM

Business

4 mins read

Grit blasting, preparation and final painting works continue to parts of the Grade II listed Corporation Road Bridge in Grimsby.

 

To take advantage of anticipated low tide levels, weekend working will continue to take place in May.

 

The South footway is now closed for the remaining duration of the works.

 

Footway closures are also required to the North footway whilst works are taking place adjacent to public areas to ensure the safety of both the public and the workers on site.

 

To help complete remaining sections of the works, the footway may be closed for 1 or 2 days a week if conditions allow.

 

Footway closures will take place between 9am and 4pm each weekday as detailed below. The footway will remain open during the weekend working dates. Temporary signs will be in place for the footway closures.

 

Paving works will also commence in May and there will be no direct access from the Riverside walkway onto Corporation bridge.

 

May 2025 weekend working and footway closure dates:

 

North Footway Closures (9am-4pm)

 

  • Wednesday 7 May

 

  • Wednesday 14 May

 

  • Wednesday 21 May

 

  • Wednesday 28 May

 

Weekend working      

        

  • Saturday 3 May and Sunday 4 May

 

  • Saturday 10 May and Sunday 11 May

 

  • Saturday 17 May and Sunday 18 May

 

North East Lincolnshire Council, its delivery partner, Equans, and contractor, Spencer Group, would like to thank the public for their patience whilst the work is being undertaken.

 

As Corporation Road Bridge is a construction site, it is important that the public respect the access restrictions in place, which have been introduced for safety reasons. Members of the public are reminded to please stay outside of all encapsulated and other working areas for their own safety, as well as that of those working there.

 

Visit https://investnel.co.uk/grimsby-developments/corporation-road-bridge-refurbishment-scheme/ to keep up to date with the Corporation Road Bridge works.

Other Articles You Might Like

Joanne

12/9/2025 9:56:35 AM

Dr. Sheeraz Janjua (2)
Dr. Sheeraz Janjua is a dedicated medical professional known for his commitment to patient-centered care and his thought...
Achievements 4 min read

Chris

4/14/2025 10:26:17 AM

South Holland District Council encouraging residents to commemorate VE Day this year
Residents across the District are encouraged to organise and to join in with local celebrations and festivities, includi...

Chris

2/11/2025 9:21:51 AM

Anglian Water work on water leak on Peaks Lane
Anglian Water have responded to a water leak on Peaks Lane, New Waltham. An emergency road closure has been put in place...
Business 3 min read

Chris

8/13/2025 3:03:45 PM

VJ Day: Bomber Research to Include Far East Losses for First Time
The International Bomber Command Centre in Lincoln has announced that the next phase of its research into losses sustain...