Home > Latest News > Business > Corporation Road Bridge Update: Footway closures and weekend working in May 2025

Corporation Road Bridge Update: Footway closures and weekend working in May 2025

Chris

5/6/2025 10:15:00 AM

Business

4 mins read

Grit blasting, preparation and final painting works continue to parts of the Grade II listed Corporation Road Bridge in Grimsby.

 

To take advantage of anticipated low tide levels, weekend working will continue to take place in May.

 

The South footway is now closed for the remaining duration of the works.

 

Footway closures are also required to the North footway whilst works are taking place adjacent to public areas to ensure the safety of both the public and the workers on site.

 

To help complete remaining sections of the works, the footway may be closed for 1 or 2 days a week if conditions allow.

 

Footway closures will take place between 9am and 4pm each weekday as detailed below. The footway will remain open during the weekend working dates. Temporary signs will be in place for the footway closures.

 

Paving works will also commence in May and there will be no direct access from the Riverside walkway onto Corporation bridge.

 

May 2025 weekend working and footway closure dates:

 

North Footway Closures (9am-4pm)

 

  • Wednesday 7 May

 

  • Wednesday 14 May

 

  • Wednesday 21 May

 

  • Wednesday 28 May

 

Weekend working      

        

  • Saturday 3 May and Sunday 4 May

 

  • Saturday 10 May and Sunday 11 May

 

  • Saturday 17 May and Sunday 18 May

 

North East Lincolnshire Council, its delivery partner, Equans, and contractor, Spencer Group, would like to thank the public for their patience whilst the work is being undertaken.

 

As Corporation Road Bridge is a construction site, it is important that the public respect the access restrictions in place, which have been introduced for safety reasons. Members of the public are reminded to please stay outside of all encapsulated and other working areas for their own safety, as well as that of those working there.

 

Visit https://investnel.co.uk/grimsby-developments/corporation-road-bridge-refurbishment-scheme/ to keep up to date with the Corporation Road Bridge works.

Other Articles You Might Like

Chris

7/8/2025 8:43:45 AM

Freshney Place set to house temporary Grimsby Town Centre pop-up library
A temporary pop-up library is set to open in Grimsby’s Freshney Place, as investigations continue into work needed at th...
Business 4 min read

Chris

2/5/2025 9:27:55 AM

Cadent Gas equipment upgrade works on Weelsby Road
Cadent Gas are in the process of carrying out upgrades to equipment on Weelsby Road, Hainton Avenue and Peaks Lane. 
Transport 3 min read

Chris

9/15/2025 2:21:51 PM

The Faroe Islands come to Grimsby Fishing Heritage Centre!
A group of officials from the Faroe Islands made the trip to Grimsby Fishing Heritage Centre to see what it’s all about.
Entertainment 4 min read

Chris

2/28/2025 9:59:28 AM

South Holland District Council sets balanced budget that supports economic growth
South Holland District Council has set its balanced budget for the next year, prioritising ways to maximise income, supp...
Business 4 min read