Corporation Road Bridge Update: Footway closures and weekend working in May 2025

Chris

5/6/2025 10:15:00 AM

Business

4 mins read

Grit blasting, preparation and final painting works continue to parts of the Grade II listed Corporation Road Bridge in Grimsby.

 

To take advantage of anticipated low tide levels, weekend working will continue to take place in May.

 

The South footway is now closed for the remaining duration of the works.

 

Footway closures are also required to the North footway whilst works are taking place adjacent to public areas to ensure the safety of both the public and the workers on site.

 

To help complete remaining sections of the works, the footway may be closed for 1 or 2 days a week if conditions allow.

 

Footway closures will take place between 9am and 4pm each weekday as detailed below. The footway will remain open during the weekend working dates. Temporary signs will be in place for the footway closures.

 

Paving works will also commence in May and there will be no direct access from the Riverside walkway onto Corporation bridge.

 

May 2025 weekend working and footway closure dates:

 

North Footway Closures (9am-4pm)

 

  • Wednesday 7 May

 

  • Wednesday 14 May

 

  • Wednesday 21 May

 

  • Wednesday 28 May

 

Weekend working      

        

  • Saturday 3 May and Sunday 4 May

 

  • Saturday 10 May and Sunday 11 May

 

  • Saturday 17 May and Sunday 18 May

 

North East Lincolnshire Council, its delivery partner, Equans, and contractor, Spencer Group, would like to thank the public for their patience whilst the work is being undertaken.

 

As Corporation Road Bridge is a construction site, it is important that the public respect the access restrictions in place, which have been introduced for safety reasons. Members of the public are reminded to please stay outside of all encapsulated and other working areas for their own safety, as well as that of those working there.

 

Visit https://investnel.co.uk/grimsby-developments/corporation-road-bridge-refurbishment-scheme/ to keep up to date with the Corporation Road Bridge works.

Other Articles You Might Like

Chris

1/29/2025 3:44:00 PM

Council staff to take place in The Great Grimsby Sleep Out
The annual Great Grimsby Sleep Out is set to take place on the 7th February 2025. The event aims to raise vital funds fo...

Chris

11/20/2024 1:48:35 PM

Planning submitted for new mixed-use development of the Crown House site
Boston Borough Council has submitted a planning application for the redevelopment of the Crown House site on the Rosegar...
Business 4 min read

Chris

6/12/2025 11:14:45 AM

More than £145,000 awarded for the continuation of successful projects supported by the UK Shared and Rural England Prosperity Funds
Several projects funded by the UK Shared and Rural England Prosperity Funds (UKSPF/REPF) have been granted permission to...
Business 4 min read

Chris

4/28/2025 8:33:25 AM

“They’re looking forward to it enormously”: Community centre thrilled by Grant Thorold Park PlayZone
A new state of the art facility will provide a range of opportunities for the East Marsh community.
Entertainment 4 min read