Corporation Road Bridge Update: Footway closures and weekend working in February 2025

Chris

1/30/2025 10:20:13 AM

Business

4 mins read

Major restoration works to Grade II listed structure, Corporation Road Bridge, have continued, with coverings removed from large sections.

 

Control room works near completion, grit blasting is ongoing to Span 5 and Span 6. These works will make way for a final assessment to determine any further required repairs.

 

Scaffold removal is in progress to Spans 2 and 3 and final painting works to these sections are also underway. With sections of the bridge having undergone full paintworks and other areas still to be completed, passers by can now see parts of the uncovered structure, showcasing the impressive repairs.

 

To take advantage of anticipated low tide levels, weekend working will take place next month.

 

Footway closures are also required whilst works are taking place adjacent to public areas to ensure the safety of both the public and the workers on site.

 

To help complete remaining sections of the works the footway may be closed for 2-days a week if conditions allow.

 

Footway closures will take place between 9am and 4pm each weekday as detailed below. The footway will remain open during the weekend working dates. Temporary signs will be in place for the footway closures.

 

February 2025 weekend working and footway closure dates:

 

South Footway Closures

 

  • Tuesday 4 February

 

  • Wednesday 5 February

 

  • Tuesday 11 February

 

  • Wednesday 12 February

 

  • Tuesday 18 February

 

  • Wednesday 19 February

 

  • Tuesday 25 February

 

  • Wednesday 26 February

 

Weekend working

 

  • Saturday 8 February and Sunday 9 February

 

  • Saturday 22 February and Saturday 23 February

 

North East Lincolnshire Council, its delivery partner, Equans, and contractor, Spencer Group, would like to thank the public for their patience whilst the work is being undertaken.

 

As Corporation Road Bridge is a construction site, it is important that the public respect the access restrictions in place, which have been introduced for safety reasons. Members of the public are reminded to please stay outside of all encapsulated and other working areas for their own safety, as well as that of those working there.

 

Visit InvestNEL | Corporation Road Bridge Major Restoration - InvestNEL to keep up to date with the Corporation Road Bridge works.

Other Articles You Might Like

Stuart

3/14/2024 1:28:10 PM

Dobbies’ Boston store invites nominations for national community initiative
Dobbies, the UK’s leading garden centre, today launches Dobbies Community Gardens, to offer support for community and ch...
Achievements 3 min read

Chris

11/6/2024 9:55:36 AM

Action to combat household damp and mould
A new damp and mould team is in place at South Kesteven District Council – to ensure a timely response to alerts from co...

Chris

2/19/2025 11:21:46 AM

Tree planting continues across the borough with help of local schools
Children and young adults from local schools have contributed to the Council’s Greening Up Our Place programme by helpin...
Nature 4 min read

Chris

7/10/2025 10:12:41 AM

A Greater Lincolnshire for All – Launched
Ambitious proposal for future of Greater Lincolnshire’s local government: 10 public pledges made to the people and commu...
Business 4 min read