Corporation Road Bridge update: Footpath closures and weekend working in September 2024

Chris

8/28/2024 7:23:04 AM

Business

3 mins read

Works to Grade II listed structure, Corporation Road Bridge, have been progressing.

Final underdeck repair works continue to Spans 1- 4 and further design works have been progressing to lifting section of Span 4.

Painting works continue to Spans 1 and 2 and 3 and these works are nearing completion. Final painting has been completed on the North trusses of Spans 5 and 6 as well as to the counterweight area. With most sections of the bridge having undergone full painting works and sections of scaffolding soon to be removed, it is easy to imagine how impressive the restored structure will be once reopened.

To take advantage of anticipated low tide levels, weekend working is required. Footpath closures are also required whilst works are taking place adjacent to public areas to ensure the safety of both the public and the contractor.

Footpath closures will take place between 9am and 4pm each weekday. The footway will remain open during the weekend working dates. Temporary signs will be in place for the footway closures.

September 2024 weekend working and footway closure dates

Footway closures:

  • Wednesday 4 September
  • Thursday 5 September
  • Wednesday 11 September
  • Wednesday 18 September
  • Thursday 19 September
  • Wednesday 25 September.

Weekend Working:

  • 31 August and 1 September
  • 8 September (Sunday ONLY)
  • 14 and 15 September
  • 28 and 29 September.

North East Lincolnshire Council, its delivery partner, Equans and contractor, Spencer Group, would like to thank the public for their patience whilst the work is being undertaken.

 As Corporation Road Bridge is a construction site, it is important that the public respect the access restrictions in place, which have been introduced for safety reasons.  Members of the public are reminded to please stay outside of all encapsulated and other working areas for their own safety, as well as that of those working there.

Visit InvestNEL (InvestNEL | Corporation Road Bridge Major Restoration - InvestNEL) to keep up to date with the Corporation Road Bridge works.

Other Articles You Might Like

Chris

7/31/2025 3:17:39 PM

Freshney Place western end transformation continues
Demolition is well underway at the western end of Freshney Place as part of the leisure scheme.
Business 4 min read

Chris

9/10/2025 8:30:57 AM

‘Changing the narrative’ this World Suicide Prevention Day
Suicide is a major public health challenge, with more than 700,000 deaths each year globally, and many more making suici...

Chris

12/20/2024 10:42:12 AM

Council leader reflects on a year of decisions and looks forward to positive change in 2025.
Cllr Philip Jackson, the Leader of North East Lincolnshire Council, pictured at the Alexandra Dock housing site in Grims...
Business 4 min read

Chris

2/26/2025 1:30:17 PM

Community tree planting begins
The first trees have gone into the ground as part of a new initiative to support biodiversity and improve the local envi...
Nature 4 min read