Home > Latest News > Business > Corporation Road Bridge update: Footpath closures and weekend working in January 2025
Chris
12/20/2024 11:21:16 AM
4 mins read
Recent activities have seen the control room roofing works and steelwork repairs completed. Parts of the scaffolding and encapsulation have been removed from this area and scaffolding has been relocated to other underdeck spans in accordance with marine management requirements. Repair works to these spans is to be assessed.
New areas of the structure are currently being grit blasted and base coat painting has commenced.
To take advantage of anticipated low tide levels, weekend working will take place next month. Footway closures are also required whilst works are taking place adjacent to public areas to ensure the safety of both the public and the workers on site.
Footway closures will take place between 9am and 4pm each weekday. The footway will remain open during the weekend working dates. Temporary signs will be in place for the footway closures.
January 2025 weekend working and footway closure dates:
South Footway Closures
Weekend Working
North East Lincolnshire Council, its delivery partner, Equans, and contractor, Spencer Group, would like to thank the public for their patience whilst the work is being undertaken.
As Corporation Road Bridge is a construction site, it is important that the public respect the access restrictions in place, which have been introduced for safety reasons. Members of the public are reminded to please stay outside of all encapsulated and other working areas for their own safety, as well as that of those working there.
Visit InvestNEL | Corporation Road Bridge Major Restoration - InvestNEL to keep up to date with the Corporation Road Bridge works.